5-Year Outdoor Facilities Plan

What does it mean to be a Game Changer?
PROJECT OVERVIEW


MEDIA LINKS
Facilities Plan Statement
High schools will no longer use Holt Arena for football games 2-18-2022
School District 25’s use of Holt Arena to end this fall upon completion of high school stadiums 2-20-2022
SD25 football to start season outdoors at schools before moving indoors at Holt 7-18-2021
District approves $1M partnership for new Poky High football field 8-18-2021
Pocatello High School to get new stadium through $1 million partnership with Lookout Credit Union 8-17-2021
New athletic fields for Pocatello Schools 2-2-2020
PHS Improvement Project
Cheryl Spall showing off the new front entrance.
As part of our Capital Improvement Plan, the Board of Trustees for the Pocatello/Chubbuck School District 25 has selected an architect firm to lead the project for improvements to Pocatello High School. The current status of the project is in the planning, design and concept phase. The goals and objectives for the project are to:
- Increase student safety by connecting main building with auditorium and gym areas.
- Provide ADA accessibility to main and upper floors of PHS and new areas.
- Provide additional classrooms and “commons” area to accommodate increased student enrollment.
- Create a clear main entrance and centrally located administrative offices.
- Help alleviate lunch room congestion and lack of space in basement cafeteria.
Follow updates on the improvements to Pocatello High School here
Updated Design - Phase II
_page_09.jpg?id=4185&width=1000)
Supporting Documents
Updated Design - Main Entrance
View project timeline
June 3, 2019: Construction slated to begin on phase one.
Historical Entry 1 | Historical Entry 2 | Historical Entry 3
Administrative Offices Floor Plan

Phase II Floor Plan:
https://v3.boardbook.org/Public/PublicItemDownload.aspx?ik=44278449
Project History, Key Dates
- April 17, 2018: Original RFP published
- April 22, 2018: RFP republished
- September 6, 2018: Special Meeting, architectural services presentations (public notice)
- September 7-14: Public comment period
- September 11, 2018: Board of Trustees, Work Session
- September 18, 2018: Regular Board Meeting, overview of presentations, public comment, decision to award project postponed (public notice)
- September 25, 2018: Special Meeting, award contract for architectural services, contract awarded to Hummel Architects (public notice)
- October 9, 2018: Board of Trustees, Regular Board Meeting
- November 20, 2018: Board of Trustees, Regular Board Meeting
- December 11, 2018: Board of Trustees, Work Session
- December 13, 2018: Kick-off meeting with Hummel Architects
- December 18, 2018: Board of Trustees, Regular Board Meeting
- January 8, 2019: Board of Trustees, Work Session
- January 15, 2019: Board of Trustees, Regular Board Meeting
- January 15, 2019: Board of Trustees voted to approve 2019-2020 Capital Improvement Program (CIP) Plan
- January 18, 2019: Follow-up meeting with Hummel Architects, Education Center, 3115 Pole Line Road
- January 31, 2019: Meet with City of Pocatello Public Works Department and staff
- February 12, 2019: Board of Trustees, Regular Board Meeting
- February 12, 2019: Meet with City of Pocatello Planning and Zoning Department and staff
- February 20, 2019: Certificate of Appropriateness awarded by the City of Pocatello Historic Preservation Commission for the main entrance design of Pocatello High School
- March 12, 2019: Board of Trustees, Regular Board Meeting
- April 9, 2019: Board of Trustees, Work Session
- April 16, 2019: Board of Trustees, Regular Board Meeting
- May 7, 2019: Board of Trustees, Work Session
- May 21, 2019: Board of Trustees, Regular Board Meeting
- June 3, 2019: Construction slated to begin on phase one.
- June 4, 2019: Meeting with Hummel Architects Re: Phase II (Alameda Middle School)
- June 18, 2019: Board of Trustees, Regular Board Meeting
- July 3, 2019: Meeting with Hummel Architects RE: Phase II budget
- July 3, 2019: City of Pocatello Historic Preservation Commission, Phase II Design - approval denied
- August 1, 2019: City of Pocatello Council approves certificate of appropriateness from Historic Preservation Commission for phase 2 of the project.
- November 15, 2019: PCSD 25 hosts ribbon cutting to mark completion of first phase of renovations.
- February 18, 2020: PCSD 25 Board of Trustees votes to award construction bid for phase two to Starr Corporation.
- April 2020: Construction of phase two begins.
Next Steps
- Phase two projected to be complete by beginning of academic school year 2021/2022.
DESIGN 1 (Awarded Contract) |
DESIGN 2 |
 |
 |